A483/A489 Newtown Bypass

Civil Infrastructure

Powys

95 million

Project Highlights

Welsh Government

Civil Infrastructure

£95 million

Alun Griffiths Contractors

Alun Griffiths Contractors

NEC3

Owner

Sector

Project Value

Principle Contractor

Client

Contract Type

Project Overview

The design and build of the Newtown Bypass is intended to ease congestion along the A483 and A489 trunk roads that originally converged in the centre of Newtown. There was also an issue with 2 low railway bridges within Newtown which caused regular traffic problems.

The bypass consists of 6.5km of a new wide single 2+1 carriageway, with 1km of new side roads, 5 new roundabouts. 11 retaining walls, 4 underpasses, 4 underbridges and 3 overbridges. In addition, extensive earthworks and ground improvement works were required.

Services Provided

  • Successful tender bid and live project support

  • Site visits and regular client meetings

  • Target cost programme support

  • Tender submission layout

  • Programme narratives

  • Cl31 Programme

  • Cl32 Programme updates

  • Cl62 Impact programmes

  • Extensive STATS planning and mitigation incl. management matrix

  • Design programme management

  • Resource loaded programmes

  • Quantity take offs / outputs matrix

  • Earthworks mass haul

  • Tilos time chainage

  • Extensive phasing plans

How we made a difference

Plan Ahead provided key support during the tender phase, development of the target cost programme and during the live project. We developed a trusted working relationship with the project manager and the client planner to enable collaborative contract programme management.

This ensured the project was completed on time and with minimal programme impact due to the effective and proactive management of early warnings.